The Adani Power thermal plant at Pirpainti: what is recorded, who claims what, and what is still unknown

The 2,400 MW coal plant under construction in Bhagalpur: the project's facts, what farmers and reports claim about land, trees, compensation and the Adivasi hamlets, the company's and officials' responses, the NGT case -- and where the figures do not agree.

In Pirpainti block, Adani Power Ltd is building a 2,400 MW (3 x 800) ultra-supercritical coal-fired power station, which PARI describes as one of the biggest plants in Bihar. The largest plant already operating in the district is NTPC's Kahalgaon station. The project is at the centre of sharp disputes over land, trees, compensation, Adivasi hamlets and environmental clearance. This article sets out what is recorded, who claims what, what the company and officials have said, and where the figures do not agree. We have not independently checked any allegation; each statement says whose it is.

The project's facts

The project belongs to the Bihar State Power Generation Company (BSPGCL) and was won by Adani Power in a bid; according to Newslaundry (read in full) the auction was held on 16 July 2025 and the letter of award is dated 28 August 2025. [Report] The same report says the project was conceived in 2006, a 2014 memorandum with NHPC lapsed, a later solar plan with NTPC did not materialise either, and it was revived as a thermal plant in February 2024. [Report] According to Global Energy Monitor (search extract) the Bihar government approved construction in March 2025. [Report]

The environmental clearance (EC) for the first phase was granted on 15 April 2026; the expert appraisal committee had recommended it in March 2026. [Report] According to PARI (read in full) work began in early 2026, and coal will come on a new broad-gauge line from the Rajmahal area. [Report] L&T (search extract) said on 9 July 2026 that it had begun dispatching structural material for Unit 1. [Report] According to Global Energy Monitor, the Central Electricity Authority's May 2026 report on projects under construction listed its physical progress at 0 per cent. [Report]

According to Newslaundry, Adani Power applied on 29 August 2026 for a second-phase clearance, adding three more 800 MW units to take capacity to 4,800 MW, with about 55 hectares more land. [Report] Another report (Patna Press, 13 October 2026, search extract) mentions the need for extra water and clearances and an estimate of 10,000 to 12,000 direct jobs during construction. [Report] We found no source saying the second phase has been cleared.

Where the figures do not agree

Cost: about Rs 25,000 crore (The Wire, September 2025, search extract), Rs 28,225 crore (PARI) and Rs 30,000 crore (Newslaundry). Land: according to Newslaundry the letter of award gives about 1,200 acres (486 hectares) on a 25-year lease at Re 1 per acre per year; The Wire (search extract) gives 1,020 acres, 25 years, Re 1 per acre per year, and Global Energy Monitor (search extract) also gives about 1,020 acres (413 hectares); PARI gives about 479 hectares for 33 years, of which 400 hectares are private and 79 hectares state land; and Newslaundry says the EC itself cites 479 hectares. An earlier report (2025, search extract) gave the site as 374 hectares. [Disputed] We did not find the reason for the differences, and we have not seen the lease itself.

Trees: how many were or will be cut

According to Newslaundry the numbers fell from document to document: in a reply before the bid (June 2025 by the file's details) a prospective bidder cited more than 3 lakh trees over about 400 acres; the District Magistrate told Dainik Bhaskar in September 2025 that an official 2010 survey found 61,363 trees (15,000 mango and 44,000 bamboo); the NGT committee's report, citing a Forest Department letter of October 2025, counts 19,388 trees, of which 15,691 are cleared for felling and 3,697 for transplanting; while the farmers' organisation's NGT petition says 5 to 10 lakh fruit-bearing trees, about 5 lakh of them mango. [Disputed] Newslaundry said it could not independently verify the true number. PARI says lakhs of fruit trees, mango among them, have been uprooted; that is its finding, not a count. The area is known for mangoes such as Jardalu (see our article on the Jardalu mango).

Compensation

The District Magistrate told Dainik Bhaskar in 2025 that the land was acquired in two rounds, 2010-11 and 2013; cases before 2013 were handled under the 1894 Act and later ones under the 2013 land acquisition law (LARR), hence the differences in rates. [Report] According to the farmers' organisation's leader, about 700 of 988 farmers received some compensation, between 120 and 180 per cent of market rates, whereas LARR provides four times in rural areas; that is his claim. [Unconfirmed] According to Newslaundry, an August 2026 Patna High Court judgment (in one farmer's case) records a BSPGCL affidavit admitting that 100 per cent compensation was not paid to some farmers, and many others are in similar litigation. [Report] Farmers also say they were not compensated for mango trees. [Unconfirmed] A further argument, that land taken in NTPC's name was handed to Adani, has not been tested in their case under the LARR provisions, according to Newslaundry. [Unconfirmed]

The public hearing and the NGT

The public hearing was held on 29 January 2026. According to the farmers' organisation leader and an elected panchayat head, dissenting farmers were held by police and given administrative notices to furnish peace bonds (Newslaundry gives this as Section 126 of the Bharatiya Nagarik Suraksha Sanhita; PARI writes "BNS"). [Unconfirmed] An official of the block office told Newslaundry, without giving his name, that panchayat heads from distant villages had been invited; a panchayat head who was invited said the hearing was peaceful and local people supported the project. [Disputed] According to PARI the document prepared after the hearing carries 447 signatures, none of them Santhal; a pollution-board official (since transferred) told PARI the crowd was huge so many could not sign. [Report]

The NGT's Kolkata bench, on the farmers' organisation's petition, constituted a joint committee (State Pollution Control Board, the Bhagalpur District Magistrate and the Environment Ministry) on 24 March 2026. Its report came on 20 July, the tribunal took it on record on 24 July, and the next hearing was set for 1 September. [Report] According to the report, the relevant permissions were in place (Forest Department permissions of October and December 2025 and the EC of 15 April 2026) and the petition's statements are "not true". [Report] Newslaundry's criticisms: the report is silent on the central allegation that felling and construction began before the EC; the committee did not take statements from the petitioner or affected people; the appraisal committee's minutes say no court case was pending when the NGT case had been filed in January; and the environmental impact assessment has no cumulative-impact assessment despite Kahalgaon's proximity. [Report] We did not find what happened after the September hearing.

The Adivasi hamlets

According to PARI (read in full), 68 families from two hamlets inside the project site (52 Sauria Paharia, a particularly vulnerable tribal group, and 16 Santhal) are to be displaced; they had no land papers, and the environmental impact assessment does not mention them. [Report] At the new site, about 5 km away, 71 rooms of 10 x 12 feet are being built; residents allege they are small and have no pillars and asbestos roofs; a contractor agreed, but PARI could not verify this independently. [Unconfirmed] The Block Development Officer told PARI that the Adivasis will get ownership rights and that all 68 families were given residential land papers on 11 October. [Report] Residents also say two burial grounds and at least three religious places fall inside the plant area, and a Circle Officer said "they are getting land for everything". [Report] PARI's postscript describes a police and excise raid on one hamlet in the last week of September in which seven people were arrested; residents see it as pressure to leave, while a senior excise official confirmed the raid and called it nothing unusual. [Disputed]

Residents also claim that groundwater has fallen since excavation began, that handpumps give yellow water, and that red dust blows; PARI's reporter saw yellow water. [Unconfirmed] On jobs, a local labourer told Newslaundry that about 150 of 400 workers are local. [Unconfirmed]

The company's response

In a statement to Newslaundry an Adani Power spokesperson said the company "unequivocally rejects" any suggestion of violating laws or regulations, is fully compliant with all statutory provisions, approvals and processes, works with local residents on livelihoods and jobs, and that the project will be important for power availability and employment in Bihar. [Report] PARI emailed Adani Power a detailed questionnaire twice and said it would update the story on a reply; we did not find a reply. Newslaundry also sought comment from the district administration and the Environment Ministry and said it would update the report when they respond.

What we don't know

We did not find what happened at the NGT after 1 September; the status of the second-phase clearance; the district administration's and the Environment Ministry's replies; the lease and the letter of award themselves; the true tree count; how many farmers have been paid in full; or any commissioning date. Both main reports belong to investigative or advocacy-minded series (Newslaundry's "Project Vande Mataram" and a PARI fellowship) and we read both in full; that is why every claim above carries its source. For block-level figures see Pirpainti block's employment structure.

Sources

  • Newslaundry (28 October 2026): land, trees, compensation, the public hearing, the NGT, the company's statement (read in full)
  • PARI (27 October 2026): the Adivasi hamlets, the lease, the cost (read in full)
  • Global Energy Monitor: project history and the May 2026 Central Electricity Authority status (search extract)
  • L&T (9 July 2026); Patna Press (September 2025 and 13 October 2026); The Wire (September 2025) (search extracts)