Four-lane roads around Bhagalpur, 2026: Munger-Mirzachowki and Bhagalpur-Bhaljor -- what is reported, and how the dates have moved
The four packages of the Munger-Mirzachowki four-lane (target dates of 15 November, 20 November and 31 December), the Rs 1,720 crore Bhagalpur-Bhaljor project, and what we did not find.
Attention has turned to four-lane roads since the Vikramshila Setu closed. This article covers reports to 3 November 2026. We read the FirstBihar report of 8 October in full; everything else comes from search extracts of Prabhat Khabar and other outlets, because the pages would not open. We have seen no government order or NHAI notice, and we name no officials. Dates are targets, not confirmation that anything has opened.
The Munger-Mirzachowki four-lane
This NHAI greenfield four-lane began in 2022, is being built in four packages, and runs from Munger through Sultanganj, Bhagalpur, Ghogha, Kahalgaon and Pirpainti to Mirzachowki; a May report gives its total length as 124.41 km. [Report] The same report says the distance now takes 4 to 5 hours and will take 1.5 to 2 hours once the road is in use. [Report] Our NTPC Kahalgaon article mentions fly ash being used on this corridor.
The four packages, from September search extracts (Prabhat Khabar, about 16 September; Varta, 22 September): Package 1 (Munger, Janaki Nagar to Khariya village): 22.56 km, of which 20.20 km built, cost ₹845.27 crore, 87.14 per cent of the work done, probable completion 15 November 2026. Package 2 (Bhagalpur): 29.42 km of 29.42 km, ₹902 crore, 96.90 per cent, 20 November 2026. Package 3 (Bhagalpur): 32.35 km, of which 25.90 km built, ₹1,017 crore, 82.74 per cent, 31 December 2026. [Report] We did not see Package 4’s September row; in the May report its cost was ₹892 crore and its progress 90.71 per cent. [Report]
How the dates have moved. The May report had the road finished by June. [Report] Reports around 12 September expected vehicles on the Munger-Bhagalpur section after Durga Puja, with about two kilometres of work at the start in Munger and the shifting of power towers still to do. [Report] Mid-September reports give 15 November for Package 1, 20 November for Package 2 and 31 December for Package 3. [Report] Prabhat Khabar (search extract) gives land acquisition, a shortage of soil and delays in getting ash from NTPC as the causes, and says the project is more than two years behind. [Report] As of today we cannot say when any section will open; Package 1’s date of 15 November is now 12 days away.
Our arithmetic (not the reports’): the four packages’ September costs add up to 845.27 + 902 + 1,017 + 892 = ₹3,656.27 crore, which matches the September report’s total, whereas the May report gave ₹3,792 crore because it put Package 1 at ₹981 crore. We did not find the reason for the change. [Unconfirmed] If the 124.41 km total is right, Package 4 would be about 40.08 km long. [Unconfirmed]
The link to the Vikramshila Setu. Heavy vehicles have been off the Vikramshila Setu since May, and after it closed completely on 1 October, Deshaj Times (search extract) reports, all traffic between north Bihar, Kosi and Seemanchal came onto Munger’s Shrikrishna Setu and the four-lane under construction; the first day was smooth, but a risk of jams ahead was noted. [Report] The reports expect the four-lane, once in use, to ease the load on both bridges. [Report] See our article on the bridge repair and this one on the ferry.
The Bhagalpur-Bhaljor four-lane
According to FirstBihar (8 October, read in full), the Bhagalpur-Bhaljor four-lane is about 67 km long, with an estimated cost of about ₹1,720 crore. [Report] It is to be built in two phases, Bhagalpur to Kharhara and then Kharhara to Bhaljor, as part of NH-133E, the Kharhara-Bhaljor stretch being between km 36.600 and 63.630 of that highway, with a divider about 3 metres wide. [Report] The report says the tender process has advanced, that obstacles to land acquisition have been removed and that preparations to start construction are under way, benefiting Bhagalpur and Banka and easing the way to Jharkhand. [Report] It gives no start date, contractor or completion time.
Our arithmetic, and what does not match: by the kilometre markers given, the Kharhara-Bhaljor stretch is 63.630 - 36.600 = 27.03 km; if the road starts at the highway’s zero, the total comes to 63.63 km, about 3.4 km short of the report’s “about 67”, and we could not explain this. [Unconfirmed] An older Prabhat Khabar report (search extract; no date shown, listed by the search as over a year old) calls a similar road the “Bhagalpur-Hansdiha four-lane”, with a first phase from Bhagalpur to Dhaka Mod costing about ₹973 crore and both phases ₹1,973 crore. The name, the phase boundary and the cost differ from the 2026 report, so we cannot say whether it is the same project in a changed form. [Disputed]
What we did not find
Confirmation that any package has opened; Package 4’s September status; the entry and exit points and tolls at Bhagalpur; the status of the separate two-lane road planned between Bhagalpur and Mirzachowki; the Bhaljor road’s start date and contractor; and any direct notice from NHAI or the road construction department. Check official notices before you travel. For other projects under way, see our article on projects around the Ganga.
Sources
- FirstBihar (8 October 2026): the Bhagalpur-Bhaljor four-lane, ₹1,720 crore (read in full)
- Prabhat Khabar (May and September 2026): the Munger-Mirzachowki packages, progress and causes of delay (search extracts); Varta, 22 September 2026, and its copies on 22Scope and IND24 (search extracts); Deshaj Times (September-October 2026) (search extracts)
- An older Prabhat Khabar report: the Bhagalpur-Hansdiha four-lane (search extract, date unknown)