Bhagalpur's rail and metro projects: what is built, what is under way, what is only on paper (October 2026)
According to the Railway Ministry's reply in the Lok Sabha, 38 of the 97 km of the Pirpainti-Jasidih line are running, while the Bhagalpur metro, cabinet-approved in June 2024, still had no DPR as of July 2026.
Rail and metro announcements for Bhagalpur are at very different stages -- some are built, some are under construction, and some are still only proposals. This article places each project by its actual status. (We have a separate article on the district's station makeovers, and this one on the history of Bhagalpur Junction.)
What is already built
According to an August 2026 report based on the Railway Ministry's reply in the Lok Sabha (to Bhagalpur MP Ajay Kumar Mandal's question number 3934), the 51 km Pirpainti-Bhagalpur doubling (₹493 crore) and the 23 km Sahibganj-Pirpainti doubling (₹129 crore) are complete. [Report] Amrit Bharat development work at Kahalgaon, Pirpainti, Sabour and Shivnarayanpur stations is also reported complete. [Report]
What is under way
The Pirpainti-Jasidih new line: a 97 km new rail line with a sanctioned cost of ₹2,700 crore. [Report] ₹1,697 crore has been spent so far, and ₹270 crore is provided for 2026-27. [Report] Of the 97 km, 38 km has been built and is already operating. [Report] Of 613 hectares of land, 338 hectares have been acquired. [Report] Three of 31 major bridges, 45 of 119 minor bridges and 25 of 37 road overbridges are complete. [Report] By our own calculation the spending is about 63 per cent of the sanctioned cost; the report gives no percentage.
The same reply lists some other projects as under way: the 53 km Bhagalpur-Jamalpur third line (₹1,156 crore), the 177 km Bhagalpur-Dumka-Rampurhat doubling (₹3,169 crore), and the 77 km Ajgaibinath Dham (Sultanganj)-Katoria new line (₹291 crore). [Report] At Bhagalpur Junction, work is described as under way on lifts, escalators, a modern station building and a better circulating area. [Report] The report gives no completion date for any of these. The Katoria figure (₹291 crore for 77 km, about ₹3.8 crore per km) is far below the Pirpainti-Jasidih line (₹2,700 crore for 97 km, about ₹27.8 crore per km); we have not checked which is right or what each figure covers. [Unconfirmed]
What is at the announcement or approval stage
According to a MyBhagalpur report of 1 September 2026, MP Nishikant Dubey made several announcements after meeting Railway Minister Ashwini Vaishnaw: a 13.38 km Sabour-Gonuddham bypass (₹303.20 crore) to reduce congestion at Bhagalpur Junction; new local MEMU/DEMU services from Bhagalpur to Tarapith and Deoghar; a new sleeper Vande Bharat Express between Bhagalpur and Anand Vihar Terminal in New Delhi, whose proposal is described as awaiting Railway Board approval after an Eastern Railway report; and a plan to develop Vikramshila station at the MP's ancestral village, Bhawanpur, into an "airport-like" facility. [Report] The same report says the Railways have sanctioned about ₹4,600 crore for regional projects; the three items it names (₹3,169 crore, ₹1,156 crore and ₹303.20 crore) add up to about ₹4,628 crore, but the report does not say what its ₹4,600 crore is made of. [Report] This is a report from a local portal, and it mixes sanctioned money, proposals and announcements.
The new Bhagalpur station (Jagdishpur): according to a Prabhat Khabar report from around March 2025, the DPR for the New Bhagalpur Station at Jagdishpur had already been sent to the Railway Board; DRM Manish Kumar Gupta was quoted as saying work would begin once the Board approved. [Report] The same report says the Uttar Pradesh agency "Yati Nidhi Construction" had been given the job of preparing the DPR for both works, and that because of lack of space the rail division changed the plan and chose Jagdishpur. [Report] But the MyBhagalpur report of 1 September 2026 says the same agency has been assigned to "prepare" the DPR for the new Jagdishpur station and a comprehensive modernisation of Bhagalpur station. "DPR already sent" (2025) and "DPR assigned to be prepared" (2026) do not line up, or the later report may be describing a new scope; we could not resolve this. [Disputed]
The Bhagalpur metro: approved, but no DPR
In June 2024 the Bihar cabinet approved metro rail projects in Muzaffarpur, Gayaji, Darbhanga and Bhagalpur. [Report] RITES was given the survey and feasibility report; it was due by November 2024 but, after a process of taking suggestions, was handed to the Urban Development and Housing Department on 16 February 2025. [Report] The proposal has two corridors in each city; Bhagalpur's network is about 24 km (Gayaji 36, Muzaffarpur 21.25 and Darbhanga 18.8 km). [Report] Under the financial model, 20 per cent of the cost is to come from the Centre, 20 per cent from the Bihar government and the remaining 60 per cent from financial institutions. [Report]
According to an India Daily report of 15 July 2026, the projects in all four cities have not moved beyond the early stage: work on preparing the DPR has not begun, and there has been no official word that the process has started. When it approved the projects the government said cost, construction agency, financial model and timeline would be set only after the DPR. No construction start date has been announced; it needs the DPR, financial sanction and final approval from the Centre. [Report]
The route plan of December 2024 to January 2025: according to reports at the time, the metro alignment team handed the project map to Bhagalpur's District Magistrate. The east-west corridor ran from Saidpur in Sabour to Champanagar, about 17 km with 16 stations; a second route ran from Station Chowk to Jagdishpur with about six stations; together about 24 km and 22 stations. Bhagalpur Station Chowk was to be an interchange, and the plan mentioned acquiring about 20 hectares in Sabour and 12 hectares near Vastu Vihar at Jagdishpur. [Report] Those reports said the DPR would now be prepared. This route predates RITES's February 2025 report, and we do not know whether it changed afterwards.
What we don't know
We did not see the Railway Ministry's original reply, only a news report based on it. We did not find whether the Railway Board approved the Jagdishpur station DPR, whether metro DPR work began after 15 July 2026, what the expected completion dates are for the projects described as under way, or whether the metro's current route and station list match the December 2024 plan.
Sources
- Udaipur Times (15 August 2026): report based on the Railway Ministry's Lok Sabha reply (question 3934)
- MyBhagalpur (1 September 2026): MP Nishikant Dubey's rail announcements
- India Daily (15 July 2026): metro projects in four cities and the DPR position
- Prabhat Khabar (around March 2025): the New Bhagalpur Station DPR; Prabhat Khabar and News4Nation (December 2024 to January 2025): the Bhagalpur metro route