The Farakka Treaty expires December 2026: what is Bihar and Bhagalpur’s stake

Bihar isn't a party, yet it's making demands. The government itself says: no conclusive evidence directly links Farakka to erosion.

The 1996 Ganga Water Sharing Treaty — also called the Farakka Treaty — expires on 12 December 2026. The treaty is between India and Bangladesh; Bihar is not a party to it. But Bhagalpur sits on the Ganga, upstream of the Farakka Barrage, and the debate over the treaty's renewal has drawn in Bihar's flood and erosion concerns. This article sets out what the treaty says, who is asking for what, and what the government itself has told Parliament about erosion.

We tag each claim with where it comes from. [Record] means a government answer in Parliament or a committee report. [Report] means a news statement. [Unconfirmed] means a single weak source's claim.

What the treaty is

  • Signed in New Delhi on 12 December 1996, the treaty runs for 30 years with a review every five years (or earlier, if either side wants) — which puts its expiry at 12 December 2026. [Report]
  • The treaty governs only the sharing of Ganga water at the Farakka Barrage during the "lean season" (1 January to 31 May), not year-round sharing. [Report]
  • The sharing formula: if flow at Farakka is below 70,000 cusecs, the split is equal; between 70,000-75,000 cusecs, Bangladesh gets a fixed 35,000 cusecs and India the rest; above 75,000 cusecs, India gets 75,000 and Bangladesh the rest. Flow is measured in 10-day periods. [Report]
  • The Farakka Barrage was built in 1975, in West Bengal, to divert some Ganga water towards the Bhagirathi-Hooghly system and maintain flow to Kolkata. [Report]

Bihar is not a party, but is making demands

  • Bihar was not a signatory to the 1996 treaty; it is an India-Bangladesh agreement, so Bihar's concerns can only reach the table through New Delhi. [Report]
  • According to JD(U) Rajya Sabha MP Sanjay Kumar Jha, the existing treaty has not adequately accounted for Bihar's interests and should not simply be renewed in its present form. He said the future framework should consider Bihar's needs for irrigation, agriculture, drinking water and industry, along with the state's projected 2050 population. He also said the treaty's 30-year impact on Bihar had never been assessed. [Report] (via PTI, carried by ThePrint)
  • Separately, Parliament's Standing Committee on External Affairs has recommended consultation with Bihar and West Bengal on any successor arrangement, the use of updated hydrological data, and climate-change considerations — along with early talks so there is no gap after 2026. [Record] The committee's chair is also named: this Parliamentary Standing Committee (on External Affairs) is chaired by Congress leader Shashi Tharoor; the committee, in its report tabled in Parliament on 30 July 2026, said the government must initiate talks with Bangladesh. [Report] An older, direct statement also surfaced: according to a paper from the Singapore-based ISAS institute, Bihar's (then) Chief Minister Nitish Kumar himself called for decommissioning the Farakka Barrage — distinct from the expert dialogues recorded above, this is a statement at the direct political leadership level. [Report] A separate report says Bihar specifically asked West Bengal to open all Farakka Barrage gates amid rising Ganga levels and flooding — a direct request to the state where the barrage itself is located. A high-level meeting, and a direct "don't renew it" demand: JD(U) leader Sanjay Jha, along with Chief Minister Samrat Choudhary, met Finance Minister Nirmala Sitharaman and External Affairs Minister S. Jaishankar, where Farakka was mentioned, though not discussed in detail. [Report] Jha himself told PTI directly that the treaty is "not in Bihar's interest," and should not be renewed when its term ends — a position that goes further than calls for decommissioning, arguing instead that the treaty should simply be allowed to lapse. Bangladesh's own voices also surfaced: Bangladesh's opposition BNP leader Mirza Fakhrul Islam Alamgir said directly that the future of relations between the two countries hinges on the treaty's renewal. [Report] Sheikh Rokon of the Dhaka-based civil society organisation Riverine People raised a separate concern — that the treaty's narrow focus on Farakka alone ignores the river's entire course, risking long-term drying of the Sundarbans delta. [Report] Both are Bangladeshi political and civil-society voices that this article had so far recorded only lightly. A balancing fact: a technical committee formed after the devastating 2007 floods, headed by Nilendu Sanyal, did not identify Farakka as the primary cause of Bihar's floods, nor did it recommend decommissioning the barrage. [Report] That is, the political demands blaming Farakka do not fully align with the findings of an earlier official committee.

Farakka and Bihar's flood-and-erosion problem: the government's own answer

  • According to an official reply from the Ministry of Jal Shakti in Parliament, there is no conclusive evidence that Ganga water-sharing with Bangladesh has altered the river's morphology in West Bengal. The Ministry attributed erosion and sedimentation to multiple factors: floods, sediment loads, rainfall, hydrological conditions, and climate-related changes. [Record]
  • That is, the government's own position is not that the Farakka Barrage directly causes Bihar's flooding or erosion — it is described as a far more tangled question. Bihar's worry hasn't gone away regardless: according to an August 25, 2026 report (Outlook), that same Monday the Bihar government had asked West Bengal to open all gates of the Farakka Barrage as Ganga water levels rose. [Report]
  • Bihar has no separate allocation under the treaty; its argument is that India's negotiating position should account for the needs of states within the Ganga basin. [Report]

Bangladesh's demand, and India's position

  • Bangladesh's Water Resources Minister Shahiduddin Chowdhury Anee said on 8 October 2026 (the same day as our search) that Bangladesh wants to conclude a new treaty before the December deadline, and that restoring a "guarantee clause" similar to the 1977 agreement is a key priority. [Report] (UNI)
  • India's Ministry of External Affairs has said discussions on the treaty will happen through existing bilateral mechanisms — the India-Bangladesh Joint Rivers Commission. [Report]
  • Water Diplomat (April 2026) says the 86th meeting of the Joint Rivers Commission and a session of the Technical Committee on Ganga took place together in Kolkata in March 2026. [Report] A PTI report in The Tribune, updated on 2 March 2025 (read in full), describes an 86th meeting of the joint committee of technical experts and a two-day Joint Rivers Commission meeting in Kolkata on 6 and 7 March, after a Bangladeshi delegation arrived on 3 March and visited the Farakka observation site until 5 March. [Report] Both cannot be the 86th meeting, so the year is disputed; we do not know which is right, or whether a further meeting took place in March 2026. [Disputed]
  • Neither side has publicly announced a final negotiating position. The Indian Council of World Affairs has argued the treaty's expiry is an opportunity to reconsider the framework, but that is expert analysis, not declared government policy. [Report]
  • Update, another statement found: Bangladesh's State Minister for Water Resources, Forhad Hossain Azad, said on 3 October 2026 that the Farakka Treaty's renewal would follow "the path of Shaheed President Ziaur Rahman". [Report] He did not spell out exactly what that means in practice — we found no elaboration of it. This is a different minister from the one quoted above for 8 October, which shows public statements on the treaty are picking up inside Bangladesh's own government as the December deadline approaches.
  • Update, Bihar's own route in, and the numbers behind the demand: according to Outlook India (around August 2026), the state of Bihar is trying to get its own concerns factored into this central-government-led bilateral negotiation — that is, state-level concerns are finding an institutional route into the talks, even though the final decision will rest with the central government and Bangladesh. [Report] A separate report (citing The Business Standard) says Bangladesh is seeking an average of 40,000 cusecs of water and a longer term in the new treaty, while India is reportedly considering a shorter renewal of 10-15 years. [Report] (This is a separate report tied to the same 86th Joint Rivers Commission meeting already recorded on our site.)
  • Bangladesh's own large-scale response — the Padma Barrage: while talks have slowed, Bangladesh is itself building a major barrage — on the Padma River, about 180 km downstream of Farakka, at Pangsha in Rajbari district. [Report] The first phase alone is estimated at around Tk 34,608 crore (roughly $3.95 billion); construction began in July 2026. [Report] Bangladesh's State Minister for Water Resources, Shahiduddin Chowdhury Anee, said directly that the project is meant to "negate the negative impact" of India's Farakka Barrage, and requires no discussion with India since it is entirely Bangladesh's own domestic matter. [Report]
  • Another Bangladeshi demand — changing how the calculation itself works: in May 2026 talks, Bangladesh also sought a change to how future water-sharing would be calculated — not based solely on flow measured at Farakka, but also accounting for upstream withdrawals through canals and irrigation in states including Uttar Pradesh, Bihar, Jharkhand and Uttarakhand. [Report] That is, Bihar's own irrigation withdrawals could become part of this international calculation debate — India's position was reported as holding that today's actual flow at Farakka itself cannot be ignored. Update, a different, starker framing of JD(U)'s position: according to a report from Singapore-based ISAS (12 October 2026), Janata Dal (United), a key ally of Prime Minister Narendra Modi's government, has opposed the treaty's renewal. [Report] This framing reads somewhat differently and more absolutely than JD(U) MP Sanjay Kumar Jha's own statement recorded above (that the treaty should not simply be extended in its present form, and should better account for Bihar's interests) — "opposed" and "wants changes to the current form" could be two different things. We cannot say whether JD(U)'s position has hardened, or whether this is simply one report's simplification. Update, two more layers: according to Eurasia Review (14 October 2026), several reports say New Delhi has not yet given a concrete response to Bangladesh's repeated approaches, while India's Ministry of External Affairs spokesperson Randhir Jaiswal said only that all river-related matters are discussed at the Joint Rivers Commission, and that technical-level meetings continue. [Report] It also emerged that Bihar is not the only state to feel left out of the process -- West Bengal's Chief Minister Mamata Banerjee had written to Prime Minister Modi saying the move to renew the treaty was "unilateral" and that the West Bengal government was not consulted. [Report] That is, the complaint about state-level participation is not Bihar's alone. Update, an upcoming meeting and a named campaign: according to the Free Press Journal (16 October 2026), Chief Minister Samrat Choudhary and Deputy Chief Minister Vijay Kumar Chaudhary will present Bihar's concerns on flooding and Ganga water-sharing at the 19th meeting of the Ganga Flood Control Commission (GFCC) in New Delhi on 27 October 2026, chaired by Union Jal Shakti Minister C.R. Patil. [Report] The same report says JD(U) has opposed renewing the treaty in its current form, citing a specific reason -- that the Farakka Barrage contributes to silt accumulation and flooding in Bihar, and that the state's water interests have not received adequate consideration. [Report] The party has also launched a public-awareness campaign called "Nitish Samvad" across 12 districts along the Ganga, to press for the protection of Bihar's water interests. [Report] Update, an earlier meeting and a request: according to Patna Press (reporting on a meeting roughly a month before this one), Chief Minister Samrat Choudhary had personally met Union Jal Shakti Minister C.R. Patil to request that the Ganga Flood Control Commission (GFCC) retain its headquarters in Patna, arguing that Bihar is among the most flood-affected states in the Ganga basin. [Report] At the same meeting, the Chief Minister gave a figure -- that around 73 per cent of Bihar's geographical area is prone to flooding. [Report] He also sought greater funding under the Flood Management and Border Area Programme (FMBAP). Update, just before the meeting — the full agenda and 12 named districts: besides the Farakka Barrage, the agenda for this 19th GFCC meeting (27 October 2026) also includes a risk-based national flood-control master plan, river water management, the use of AI to prepare detailed project reports (DPRs), a national flood-monitoring dashboard, and flood-control SOPs and guidelines for waterways and rail-road infrastructure; the commission will also review decisions from its 18th meeting. [Report] Deputy Chief Minister Bijendra Prasad Yadav told ETV Bharat that the Ganga previously flowed through Bihar and West Bengal to the Bay of Bengal, and that the Farakka Barrage was built to provide water to Bangladesh — according to him, this is what caused silting and sharply reduced the river's depth in Bihar. [Report] This effort is focused on 12 districts along the Ganga, including Buxar, Bhojpur, Saran, Patna, Vaishali, Samastipur, Begusarai, Lakhisarai, Munger, Khagaria, Bhagalpur and Katihar — that is, Bhagalpur itself is among these named districts. [Report] JD(U) National Working President Sanjay Kumar Jha has also demanded that any future agreement take Bihar's water requirements up to the year 2050 into account. [Report] JD(U) leaders also made another, specific claim: that under the treaty, Bangladesh receives 1,500 cumecs of water during the lean season, while Bihar gets only 400 cumecs. [Claim] This is the party's own claim; we have not found confirmation of it from an independent source. A different, more cautious expert view also surfaced: according to Counterview (a report from 21 days earlier), speakers at a "Bihar Policy Dialogue" held at the Babu Jagjivan Ram Research Institute in Patna argued that Bihar's floods, water scarcity and ecological distress cannot be reduced to Farakka or international water-sharing alone — the problem is considerably wider. [Report] A committee connected to the same event also did not identify Farakka as the "primary cause" of Bihar's floods, nor did it recommend decommissioning the barrage — a more measured position than the political statements recorded above. [Report] That is, there is not just one view on Farakka — some experts do not agree that it is the sole or primary cause, even as political parties take a different line. A concrete, immediate demand, and a senior central minister's assurance: according to The Daily Star (a report from 54 days earlier), amid a flood-like situation caused by the Ganga's rising water level, Deputy Chief Minister and Water Resources Minister Vijay Kumar Choudhary demanded that all gates of the Farakka Barrage be opened, to ease the river's flow. [Report] According to him, External Affairs Minister S. Jaishankar assured Bihar that the matter would be acted upon soon. [Report] This is a separate, immediate/operational demand — distinct from the broader ongoing negotiations over the treaty's future, tied instead to an acute flood situation. A separate, written document also surfaced: External Affairs Minister S. Jaishankar wrote to JD(U) leader Sanjay Kumar Jha in a letter dated 28 August 2026, saying the government "fully understands" Jha's concerns regarding the Ganga water treaty. [Report] According to the letter, inter-ministerial discussions were held under the leadership of the Jal Shakti Ministry with various stakeholders, in which Bihar's drinking water, agricultural, and industrial water needs were duly considered. [Report] This is distinct from the earlier-recorded verbal assurance (during the flood situation) — this is a formal, dated written letter, specifically about the broader treaty-renewal negotiation. A separate, Bhagalpur-named dialogue — with the opposite conclusion: distinct from the "Bihar Policy Dialogue" held in Patna, a separate "Bhagalpur Dialogue" was also held, where speakers openly called for decommissioning the Farakka Barrage and for equitable sharing of Ganga waters — that is, this Bhagalpur-based dialogue's conclusion is directly opposite to the Patna dialogue, which had declined to call Farakka the primary cause of flooding. [Report] The Bhagalpur Dialogue also raised the impact on floodplain farmers, fishing families, and char (river-island) dwellers, and adopted a common declaration calling for an independent, credible assessment of Farakka's full effects. [Report] That is, even among experts and academics, there is no single view on this question — the conclusions from the Patna and Bhagalpur dialogues directly conflict with each other. This meeting has not taken place yet — we wrote this update a day before it; the outcome is not yet recorded.

Latest: 29 October 2026 (AFP)

The most recent account we found is an AFP report of 29 October, carried by Dawn (read in full). As of 2 November the treaty has 40 days to run; it expires on 12 December. [Report]

  • Whether talks have started. According to AFP, Bangladesh says India has not responded to its request to negotiate a renewal. India's Ministry of External Affairs says river-related discussions are a matter for the Joint Rivers Commission, which held its last technical talks in May. [Report] (The 86th meeting of March 2026 is recorded earlier in this article; the May talks are a separate technical round of which we have no details.)
  • How long since ministers met. AFP says the last officially confirmed ministerial-level meeting of the Commission was in 2022, after a gap of 12 years, and that a proposed deal on the Teesta river has been stalled since 2011. [Report]
  • No automatic extension. According to AFP the 1996 treaty has no clause extending it automatically. [Report] The report does not say what arrangement would apply from 13 December if nothing is agreed.
  • Bangladesh's position. AFP quotes Rashed Al Mahmud Titumir, a prime ministerial adviser who heads Bangladesh's technical committee on water-sharing, as saying that Bangladesh needs a new deal based on "mutual benefit and respect". A former Bangladeshi member of the Commission, Malik Fida A. Khan, said India has built more dams upstream and that a new agreement must include provisions on climate change and consider the whole river basin. [Report]
  • A possible visit. AFP says Bangladesh's Prime Minister Tarique Rahman may reportedly visit India before the treaty expires, but no visit has been confirmed. [Unconfirmed]
  • Effects described in Bangladesh. According to AFP, a representative of an environmental group said that during the years without a treaty after the earlier arrangement lapsed at least three rivers almost dried up, and that the Ganges-Kobadak irrigation project, designed to water 955 sq km, stopped working because of water scarcity; Bangladesh's state news agency BSS says it has shrunk to 550 sq km even with the treaty in place. [Report] These are Bangladeshi accounts of effects downstream and we have not verified them.
  • A figure that conflicts. AFP describes the Padma Barrage as a $2.8-billion project approved by Dhaka in May, with a 113 MW hydropower plant. Our earlier note in this article gives about $3.95 billion and says construction began in July. We have not reconciled the two figures and dates. [Disputed]

AFP's report does not mention Bihar or the Indian states along the river; what Bihar has asked for is recorded earlier in this article.

What we did not find

  • India's final negotiating position, or whether the treaty will be renewed, revised, or lapse without a new agreement.
  • India's clear position on the "guarantee clause".
  • Any study of direct effects of Farakka on Bhagalpur-area dolphins or sedimentation — our earlier articles also found no direct link documented.
  • What happened after 12 December 2026 — this article was written before that date.

What we are not claiming

  • Whether the Farakka Barrage causes Bihar's flooding or erosion — the government's own answer says there is no conclusive evidence, and lists multiple causes. We make no claim beyond that.
  • Whether the treaty will be renewed, or on what terms.
  • Anything personal from an MP, official or fisherman, beyond what is quoted above. We have not spoken to anyone.

Related

Sources

  • PTI, via The Tribune (updated 2 March 2025): the schedule of the 86th technical meeting and the Joint Rivers Commission meeting in Kolkata (read in full)
  • Outlook India, "Farakka, Floods And River Sharing: Why Bihar Wants A New Ganga Water Deal" (Sidharth Singh, 25 August 2026; read in full)
  • UNI, "Bangladesh hopes to conclude new Ganges water-sharing treaty by December" (8 October 2026; search excerpt)
  • The Tribune, "Bangladesh seeks new or revised Ganges water pact with India ahead of 2026 deadline" (8 October 2026; search excerpt)
  • Water Diplomat, "The Ganges Treaty Renewal: Negotiating Water Sharing under Climate Stress" (search excerpt)
  • Outlook India, "Ganga Water Treaty Explained: Why India And Bangladesh Are Discussing Its Renewal" (search excerpt)